This two-story ground-up building was part of Vantage Data Center’s phased campus expansion. The development added three 2.75MW Cummins Generators with 5,000-gallon belly tanks. As a mission critical facility, the design also covered uninterrupted power supply for critical components of the operation, including IT load. The project included complex interrelated building systems (such as security monitoring, cameras, building and energy management systems) to the telecommunications infrastructure connecting existing campus and data distribution.
Additional spaces included offices, conference rooms, break rooms, two data modules, electrical room, and battery room. The building has an electric capacity of 6MW of IT power.